European Commission
JRC Smart Electricity Systems

  • STATUS: Announced
  • Power: 1.2 MW
  • Capacity: 6.35 MWh
  • Duration: 5.29 hours
  • Units: 1
Technology and subtechnology
ELECTROCHEMICAL | Unspecific Storage battery

Facility

Country
Germany(Germany)
Region
North Rhine-Westphalia
Second Level
Germany
Coordinates (lat,lon):
51.870000 , 7.120000
Disclaimer: The information displayed about this project has been obtained from the dataset provided by Wood Mackenzie. Wood Mackenzie Limited, subject to any additional data modifications and/or input provided by the EC or any of its authorised 3rd party contributor.
  • STATUS: Announced
  • Power: 6.9 MW
  • Capacity: 18.97 MWh
  • Duration: 2.75 hours
  • Units: 1
Technology and subtechnology
ELECTROCHEMICAL | Unspecific Storage battery

Facility

Country
Germany(Germany)
Region
Brandenburg
Second Level
Germany
Coordinates (lat,lon):
52.890000 , 12.220000
Disclaimer: The information displayed about this project has been obtained from the dataset provided by Wood Mackenzie. Wood Mackenzie Limited, subject to any additional data modifications and/or input provided by the EC or any of its authorised 3rd party contributor.
  • STATUS: Operational
  • Power: 25 MW
  • Capacity: 29 MWh
  • Duration: 1.16 hours
  • Units: 1
Technology and subtechnology
ELECTROCHEMICAL | Unspecific Storage battery

Facility

Country
Sweden(Sweden)
Region
Skane
Second Level
Sweden
Coordinates (lat,lon):
55.890000 , 13.940000
Disclaimer: The information displayed about this project has been obtained from the dataset provided by Wood Mackenzie. Wood Mackenzie Limited, subject to any additional data modifications and/or input provided by the EC or any of its authorised 3rd party contributor.
  • STATUS: Operational
  • Power: 1.2 MW
  • Capacity: 2.4 MWh
  • Duration: 2 hours
  • Units: 1
Technology and subtechnology
ELECTROCHEMICAL | Unspecific Storage battery

Facility

Country
Hungary
Coordinates (lat,lon):
47.181759 , 19.506094
Disclaimer: The information displayed about this project has been obtained from the dataset provided by Wood Mackenzie. Wood Mackenzie Limited, subject to any additional data modifications and/or input provided by the EC or any of its authorised 3rd party contributor.
  • STATUS: Operational
  • Power: 2.21 MW
  • Estimated Capacity: 3.09 MWh
  • Duration: 1.4 hours
  • Units: 1
Technology and subtechnology
ELECTROCHEMICAL | Lithium-ion batteries

Facility

Country
Germany(Germany)
Region
Bavaria
Second Level
Germany
Coordinates (lat,lon):
50.190000 , 9.790000
Disclaimer: The information displayed about this project has been obtained from the dataset provided by Wood Mackenzie. Wood Mackenzie Limited, subject to any additional data modifications and/or input provided by the EC or any of its authorised 3rd party contributor.
  • STATUS: Operational
  • Power: 15.12 MW
  • Capacity: 30 MWh
  • Duration: 1.98 hours
  • Units: 1
Technology and subtechnology
ELECTROCHEMICAL | Unspecific Storage battery

Facility

Country
Germany(Germany)
Region
Bavaria
Second Level
Germany
Coordinates (lat,lon):
48.510000 , 11.510000
Disclaimer: The information displayed about this project has been obtained from the dataset provided by Wood Mackenzie. Wood Mackenzie Limited, subject to any additional data modifications and/or input provided by the EC or any of its authorised 3rd party contributor.