Start and end dates: 
January, 2007 to December, 2010
Prevailing Stage of Development: 
Research & Development
Brief description and/or other information regarding the project: 
The aim of this project is to design an intelligent 400 kVA. MV/LV distribution station (intDS) that will allow power flow fluctuations to be managed while maintaining power quality. reliability and security of supply. A full-scale prototype was assembled and extensively tested at the Flex Power Grid Lab (FPG Lab). It was then installed in a live test grid as a pilot.
Project full name: 
Smart Substation
Countries involved: 
Project Main Application: 
Smart Network Management